Thursday, May 15, 2008
ROOF TILES
marseilles satin brown. complete acessories. thank you very much to Cheng of Edaran Prestasi S/B and Azhar of C&G for their support.
Posted by KAHAR AMBOK LALEK at 4:41 AM 0 comments
FIRST FLOOR COLUMN
reinforcement bar for first floor column
formwork for first floor column. scaffolding shall remain for another 2 weeks.
Posted by KAHAR AMBOK LALEK at 4:25 AM 0 comments
FIRST FLOOR SERVICES
UPVC conduit, BRC A8, spacer and starter bar for first floor column. ready for concreting works
Posted by KAHAR AMBOK LALEK at 4:19 AM 0 comments
FIRST FLOOR
erecting first floor beam formwork and floor joist .
finish formwork for first floor. electrical conduit started.
Posted by KAHAR AMBOK LALEK at 4:10 AM 0 comments
TERMITE CONTROL
compacted hardcore done. anti termite to finalise work on site. site to receive DPM,BRC and Concrete
Posted by KAHAR AMBOK LALEK at 3:52 AM 0 comments
GROUND BEAM
ground beam and backfilling. Underground sewerage system in progress. Ready to receive hardcore and floor slab
Labels: GROUND BEAM
Posted by KAHAR AMBOK LALEK at 3:48 AM 0 comments
FACADE DESIGN REDEFINE
Labels: FACADE DESIGN REDEFINE
Posted by KAHAR AMBOK LALEK at 3:25 AM 0 comments
Monday, May 12, 2008
STARTER
lambat sikit upload kerana kepincangan kemudahan.
lepas aku beli "izzi" wireless broadband ni..alhamdulillah, banyak sumbangan boleh aku buat.
Posted by KAHAR AMBOK LALEK at 1:53 AM 0 comments